What actually happens during a 45-day interior project
Day by day, from site measurement to snag list — so you know whether your project is on track.
Forty-five days sounds fast until you see it broken up. Most of it is not carpentry — it is sequencing, and the projects that slip almost always slip in the first fortnight.
Days 1 to 10: design and measurement
Site measurement within 72 hours of booking. Space planning, 3D views and revisions. This is the phase where you should be demanding and slow — every change here is free, and every change after day 12 is not.
Days 11 to 14: sign-off and production release
Final drawings, material selection locked, quote frozen, and the file released to the factory. Nothing is cut before this point.
Days 15 to 32: factory production and site civil work
- Cabinetry is cut, edge-banded and pre-assembled in the factory.
- In parallel on site: demolition, electrical points, plumbing shifts, tiling.
- False ceiling framing and boarding.
- Putty, primer and first coat of paint.
Days 33 to 42: installation
Modular units arrive flat-packed and are installed room by room, kitchen first. Countertops are templated on site after base units are levelled — this is why counters arrive later than you expect.
Days 43 to 45: snagging and handover
You walk the home with your project manager and list every defect, however small. That list is closed before the final payment, not after.